dations from the agencies and Indian tribes identified in subparagraphs (A) and (B) of paragraph (2) for proposed terms and conditions for the Commission's consideration for inclusion in the license.

(b) Alterations in project works

That except when emergency shall require for the protection of navigation, life, health, or property, no substantial alteration or addition not in conformity with the approved plans shall be made to any dam or other project works constructed hereunder of an installed capacity in excess of two thousand horsepower without the prior approval of the Commission; and any emergency alteration or addition so made shall thereafter be subject to such modification and change as the Commission may direct.

(c) Maintenance and repair of project works; liability of licensee for damages

That the licensee shall maintain the project works in a condition of repair adequate for the purposes of navigation and for the efficient operation of said works in the development and transmission of power, shall make all necessary renewals and replacements, shall establish and maintain adequate depreciation reserves for such purposes, shall so maintain, and operate said works as not to impair navigation, and shall conform to such rules and regulations as the Commission may from time to time prescribe for the protection of life, health, and property. Each licensee hereunder shall be liable for all damages occasioned to the property of others by the construction, maintenance, or operation of the project works or of the works appurtenant or accessory thereto, constructed under the license and in no event shall the United States be liable therefor.

(d) Amortization reserves

That after the first twenty years of operation, out of surplus earned thereafter, if any, accumulated in excess of a specified reasonable rate of return upon the net investment of a licensee in any project or projects under license, the licensee shall establish and maintain amortization reserves, which reserves shall, in the discretion of the Commission, be held until the termination of the license or be applied from time to time in reduction of the net investment. Such specified rate of return and the proportion of such surplus earnings to be paid into and held in such reserves shall be set forth in the license. For any new license issued under section 808 of this title, the amortization reserves under this subsection shall be maintained on and after the effective date of such new license.

(e) Annual charges payable by licensees; maximum

rates; application; review and report to Congress (1) That the licensee shall pay to the United States reasonable annual charges in an amount to be fixed by the Commission for the purpose of reimbursing the United States for the costs of the administration of this subchapter, including any reasonable and necessary costs incurred by Federal and State fish and wildlife agencies and other natural and cultural resource agencies in connection with studies or

other reviews carried out by such agencies for purposes of administering their responsibilities under this subchapter; for recompensing it for the use, occupancy, and enjoyment of its lands or other property; and for the expropriation to the Government of excessive profits until the respective States shall make provision for preventing excessive profits or for the expropriation thereof to themselves, or until the period of amortization as herein provided is reached, and in fixing such charges the Commission shall seek to avoid increasing the price to the consumers of power by such charges, and any such charges may be adjusted from time to time by the Commission as conditions may require: Provided, That, subject to annual appropriations Acts, the portion of such annual charges imposed by the Commission under this subsection to cover the reasonable and necessary costs of such agencies shall be available to such agencies (in addition to other funds appropriated for such purposes) solely for carrying out such studies and reviews and shall remain available until expended: Provided, That when licenses are issued involving the use of Government dams or other structures owned by the United States or tribal lands embraced within Indian reservations the Commission shall, subject to the approval of the Secretary of the Interior in the case of such dams or structures in reclamation projects and, in the case of such tribal lands, subject to the approval of the Indian tribe having jurisdiction of such lands as provided in section 476 of title 25, fix a reasonable annual charge for the use thereof, and such charges may with like approval be readjusted by the Commission at the end of twenty years after the project is available for service and at periods of not less than ten years thereafter upon notice and opportunity for hearing: Provided further, That licenses for the development, transmission, or distribution of power by States or municipalities shall be issued and enjoyed without charge to the extent such power is sold to the public without profit or is used by such State or municipality for State or municipal purposes, except that as to projects constructed or to be constructed by States or municipalities primarily designed to provide or improve navigation, licenses therefor shall be issued without charge; and that licenses for the development, transmission, or distribution of power for domestic, mining, or other beneficial use in projects of not more than two thousand horsepower installed capacity may be issued without charge, except on tribal lands within Indian reservations; but in no case shall a license be issued free of charge for the development and utilization of power created by any Government dam and that the amount charged therefor in any license shall be such as determined by the Commission: Provided however, That no charge shall be assessed for the use of any Government dam or structure by any licensee if, before January 1, 1985, the Secretary of the Interior has entered into a contract with such licensee that meets each of the following requirements:

(A) The contract covers one or more projects for which a license was issued by the Commission before January 1, 1985.

(B) The contract contains provisions specifically providing each of the following:

(i) A powerplant may be built by the licensee utilizing irrigation facilities constructed by the United States.

(ii) The powerplant shall remain in the exclusive control, possession, and ownership of the licensee concerned.

(iii) All revenue from the powerplant and from the use, sale, or disposal of electric energy from the powerplant shall be, and remain, the property of such licensee.

(C) The contract is an amendatory, supplemental and replacement contract between the United States and: (i) the Quincy-Columbia Basin Irrigation District (Contract No. 14-06-100-6418); (ii) the East Columbia Basin Irrigation District (Contract No. 14-06-100-6419); or, (iii) the South Columbia Basin Irrigation District (Contract

14-06-100-6420).

No.

This paragraph shall apply to any project covered by a contract referred to in this paragraph only during the term of such contract unless otherwise provided by subsequent Act of Congress. In the event an overpayment of any charge due under this section shall be made by a licensee, the Commission is authorized to allow a credit for such overpayment when charges are due for any subsequent period.

(2) In the case of licenses involving the use of Government dams or other structures owned by the United States, the charges fixed (or readjusted) by the Commission under paragraph (1) for the use of such dams or structures shall not exceed 1 mill per kilowatt-hour for the first 40 gigawatt-hours of energy a project produces in any year, 11⁄2 mills per kilowatt-hour for over 40 up to and including 80 gigawatt-hours in any year, and 2 mills per kilowatt-hour for any energy the project produces over 80 gigawatthours in any year. Except as provided in subsection (f) of this section, such charge shall be the only charge assessed by any agency of the United States for the use of such dams or structures.

(3) The provisions of paragraph (2) shall apply with respect to

(A) all licenses issued after October 16, 1986; and

(B) all licenses issued before October 16, 1986, which

(i) did not fix a specific charge for the use of the Government dam or structure involved; and

(ii) did not specify that no charge would be fixed for the use of such dam or structure.

(4) Every 5 years, the Commission shall review the appropriateness of the annual charge limitations provided for in this subsection and report to Congress concerning its recommendations thereon.

(f) Reimbursement by licensee of other licensees, etc. That whenever any licensee hereunder is directly benefited by the construction work of an

other licensee, a permittee, or of the United States of a storage reservoir or other headwater improvement, the Commission shall require as a condition of the license that the licensee so benefited shall reimburse the owner of such reservoir or other improvements for such part of the annual charges for interest, maintenance, and depreciation thereon as the Commission may deem equitable. The proportion of such charges to be paid by any licensee shall be determined by the Commission. The licensees or permittees affected shall pay to the United States the cost of making such determination as fixed by the Commission.

Whenever such reservoir or other improvement is constructed by the United States the Commission shall assess similar charges against any licensee directly benefited thereby, and any amount so assessed shall be paid into the Treasury of the United States, to be reserved and appropriated as a part of the special fund for headwater improvements as provided in section 810 of this title.

Whenever any power project not under license is benefited by the construction work of a licensee or permittee, the United States or any agency thereof, the Commission, after notice to the owner or owners of such unlicensed project, shall determine and fix a reasonable and equitable annual charge to be paid to the licensee or permittee on account of such benefits, or to the United States if it be the owner of such headwater improvement.

(g) Conditions in discretion of commission

Such other conditions not inconsistent with the provisions of this chapter as the commission may require.

(h) Monopolistic combinations; prevention or minimization of anticompetitive conduct; action by Commission regarding license and operation and maintenance of project

(1) Combinations, agreements, arrangements, or understandings, express or implied, to limit the output of electrical energy, to restrain trade, or to fix, maintain, or increase prices for electrical energy or service are hereby prohibited.

(2) That conduct under the license that: (A) results in the contravention of the policies expressed in the antitrust laws; and (B) is not otherwise justified by the public interest considering regulatory policies expressed in other applicable law (including but not limited to those contained in subchapter II of this chapter) shall be prevented or adequately minimized by means of conditions included in the license prior to its issuance. In the event it is impossible to prevent or adequately minimize the contravention, the Commission shall refuse to issue any license to the applicant for the project and, in the case of an existing project, shall take appropriate action to provide thereafter for the operation and maintenance of the affected project and for the issuing of a new license in accordance with section 808 of this title.

(i) Waiver of conditions

In issuing licenses for a minor part only of a complete project, or for a complete project of not more than two thousand horsepower installed capacity, the Commission may in its discretion waive such conditions, provisions, and requirements of this subchapter, except the license period of fifty years, as it may deem to be to the public interest to waive under the circumstances: Provided, That the provisions hereof shall not apply to annual charges for use of lands within Indian reservations.

(j) Fish and wildlife protection, mitigation and enhancement; consideration of recommendations; findings

(1) That in order to adequately and equitably protect, mitigate damages to, and enhance, fish and wildlife (including related spawning grounds and habitat) affected by the development, operation, and management of the project, each license issued under this subchapter shall include conditions for such protection, mitigation, and enhancement. Subject to paragraph (2), such conditions shall be based on recommendations received pursuant to the Fish and Wildlife Coordination Act (16 U.S.C. 661 et seq.) from the National Marine Fisheries Service, the United States Fish and Wildlife Service, and State fish and wildlife agencies.

(2) Whenever the Commission believes that any recommendation referred to in paragraph (1) may be inconsistent with the purposes and requirements of this subchapter or other applicable law, the Commission and the agencies referred to in paragraph (1) shall attempt to resolve any such inconsistency, giving due weight to the recommendations, expertise, and statutory responsibilities of such agencies. If, after such attempt, the Commission does not adopt in whole or in part a recommendation of any such agency, the Commission shall publish each of the following findings (together with a statement of the basis for each of the findings):

(A) A finding that adoption of such recommendation is inconsistent with the purposes and requirements of this subchapter or with other applicable provisions of law.

(B) A finding that the conditions selected by the Commission comply with the requirements of paragraph (1).

Subsection (i) of this section shall not apply to the conditions required under this subsection. (June 10, 1920, ch. 285, pt. I, § 10, 41 Stat. 1068; renumbered pt. I and amended, Aug. 26, 1935, ch. 687, title II, §§ 206, 212, 49 Stat. 842, 847; Sept. 7, 1962, Pub. L. 87-647, 76 Stat. 447; Aug. 3, 1968, Pub. L. 90-451, § 4, 82 Stat. 617; Oct. 16, 1986, Pub. L. 99-495, §§ 3(b), (c), 9(a), 13, 100 Stat. 1243, 1244, 1252, 1257; Oct. 27, 1986, Pub. L. 99-546, title IV, § 401, 100 Stat. 3056; Oct. 24, 1992, Pub. L. 102-486, title XVII, § 1701(a), 106 Stat. 3008.)

REFERENCES IN TEXT

The antitrust laws, referred to in subsec. (h)(2), are classified generally to chapter 1 (§ 1 et seq.) of Title 15, Commerce and Trade.

The Fish and Wildlife Coordination Act, referred to in subsec. (j)(1), is act Mar. 10, 1934, ch. 55, 48 Stat. 401, as amended, which is classified generally to sec

tions 661 to 666c of this title. For complete classification of this Act to the Code, see Short Title note set out under section 661 of this title and Tables.

AMENDMENTS

1992-Subsec. (e)(1). Pub. L. 102-486, in introductory provisions, substituted "administration of this subchapter, including any reasonable and necessary costs incurred by Federal and State fish and wildlife agencies and other natural and cultural resource agencies in connection with studies or other reviews carried out by such agencies for purposes of administering their responsibilities under this subchapter;" for "administration of this subchapter;" and inserted "Provided, That, subject to annual appropriations Acts, the portion of such annual charges imposed by the Commission under this subsection to cover the reasonable and necessary costs of such agencies shall be available to such agencies (in addition to other funds appropriated for such purposes) solely for carrying out such studies and reviews and shall remain available until expended:" after "as conditions may require:".

1986-Subsec. (a). Pub. L. 99-495, § 3(b), designated existing provisions as par. (1), inserted "for the adequate protection, mitigation, and enhancement of fish and wildlife (including related spawning grounds and habitat)," after "water-power development", inserted "irrigation, flood control, water supply, and" after "including", which words were inserted after "public uses, including" as the probable intent of Congress, substituted "and other purposes referred to in section 797(e) of this title" for "purposes; and", and added pars. (2) and (3).

Subsec. (e). Pub. L. 99-546 inserted proviso that no charge be assessed for use of Government dam or structure by licensee if, before Jan. 1, 1985, licensee and Secretary entered into contract which met requirements of date of license, powerplant construction, ownership, and revenue, etc.

Pub. L. 99-495, § 9(a), designated existing provisions as par. (1) and added pars. (2) to (4).

Subsec. (h). Pub. L. 99-495, § 13, designated existing provisions as par. (1) and added par. (2).

Subsec. (j). Pub. L. 99-495, § 3(c), added subsec. (j). 1968-Subsec. (d). Pub. L. 90-451 provided for maintenance of amortization reserves on and after effective date of new licenses.

1962-Subsecs. (b), (e), (i). Pub. L. 87-647 substituted "two thousand horsepower" for "one hundred horsepower".

1935-Subsec. (a). Act Aug. 26, 1935, § 206, substituted "plan for improving or developing a waterway or waterways for the use or benefit of interstate or foreign commerce, for the improvement and utilization of water-power development, and for other beneficial uses, including recreational purposes" for "scheme of improvement and utilization for the purposes of navigation, of water-power development, and of other beneficial public uses," and "such plan" for "such scheme".

Subsec. (b). Act Aug. 26, 1935, § 206, inserted "installed" before "capacity".

Subsec. (d). Act Aug. 26, 1935, § 206, substituted "net investment" for "actual, legitimate investment". Subsec. (e). Act Aug. 26, 1935, § 206, amended subsec. (e) generally.

Subsec. (f). Act Aug. 26, 1935, § 206, inserted last sentence to first par., and inserted last par.

Subsec. (i). Act Aug. 26, 1935, § 206, inserted "installed" before "capacity", and "annual charges for use of" before "lands" in proviso.

EFFECTIVE DATE OF 1986 AMENDMENT Amendment by Pub. L. 99-495 effective with respect to each license, permit, or exemption issued under this chapter after Oct. 16, 1986, see section 18 of Pub. L. 99-495, set out as a note under section 797 of this title.

SAVINGS PROVISION

Section 9(b) of Pub. L. 99-495 provided that: "Nothing in this Act [see Short Title of 1986 Amendment note set out under section 791a of this title) shall affect any annual charge to be paid pursuant to section 10(e) of the Federal Power Act [16 U.S.C. 803(e)] to Indian tribes for the use of their lands within Indian reservations."

TRANSFER OF FUNCTIONS

Federal Power Commission terminated and its functions with regard to licenses and permits for dams, reservoirs, or other works for development and improvement of navigation and for development and utilization of power across, along, from, or in navigable waters under this subchapter transferred to Federal Energy Regulatory Commission by sections 7172(a)(1)(A) and 7293 of Title 42, The Public Health and Welfare.

SECTION REFERRED TO IN OTHER SECTIONS

This section is referred to in sections 808, 823a, 824a-3 of this title; title 42 section 7178.

§ 804. Project works affecting navigable waters; requirements insertable in license

If the dam or other project works are to be constructed across, along, or in any of the navigable waters of the United States, the commission may, insofar as it deems the same reasonably necessary to promote the present and future needs of navigation and consistent with a reasonable investment cost to the licensee, include in the license any one or more of the following provisions or requirements:

(a) That such licensee shall, to the extent necessary to preserve and improve navigation facilities, construct, in whole or in part, without expense to the United States, in connection with such dam, a lock or locks, booms, sluices, or other structures for navigation purposes, in accordance with plans and specifications approved by the Chief of Engineers and the Secretary of the Army and made part of such li

cense.

(b) That in case such structures for navigation purposes are not made a part of the original construction at the expense of the licensee, then whenever the United States shall desire to complete such navigation facilities the licensee shall convey to the United States, free of cost, such of its land and its rights-of-way and such right of passage through its dams or other structures, and permit such control of pools as may be required to complete such navigation facilities.

(c) That such licensee shall furnish free of cost to the United States power for the operation of such navigation facilities, whether constructed by the licensee or by the United States.

(June 10, 1920, ch. 285, pt. I, § 11, 41 Stat. 1070; renumbered pt. I, Aug. 26, 1935, ch. 687, title II, $212, 49 Stat. 847; July 26, 1947, ch. 343, title II, § 205(a), 61 Stat. 501.)

CHANGE OF NAME

Department of War designated Department of the Army and title of Secretary of War changed to Secretary of the Army by section 205(a) of act July 26, 1947, ch. 343, title II, 61 Stat. 501. Section 205(a) of act July 26, 1947, was repealed by section 53 of act Aug. 10,

1956, ch. 1041, 70A Stat. 641. Section 1 of act Aug. 10, 1956, enacted "Title 10, Armed Forces" which in sections 3010 to 3013 continued military Department of the Army under administrative supervision of Secretary of the Army.

TRANSFER OF FUNCTIONS

Federal Power Commission terminated and its functions with regard to licenses and permits for dams, reservoirs, or other works for development and improvement of navigation and for development and utilization of power across, along, from, or in navigable waters under this subchapter transferred to Federal Energy Regulatory Commission by sections 7172(a)(1)(A) and, 7293 of Title 42, The Public Health and Welfare.

SECTION REFERRED TO IN OTHER SECTIONS

This section is referred to in section 805 of this title. § 805. Participation by Government in costs of locks,

etc.

Whenever application is filed for a project hereunder involving navigable waters of the United States, and the commission shall find upon investigation that the needs of navigation require the construction of a lock or locks or other navigation structures, and that such structures cannot, consistent with a reasonable investment cost to the applicant, be provided in the manner specified in subsection (a) of section 804 of this title, the commission may grant the application with the provision to be expressed in the license that the licensee will install the necessary navigation structures if the Government fails to make provision therefor within a time to be fixed in the license and cause a report upon such project to be prepared, with estimates of cost of the power development and of the navigation structures, and shall submit such report to Congress with such recommendations as it deems appropriate concerning the participation of the United States in the cost of construction of such navigation structures.

(June 10, 1920, ch. 285, pt. I, § 12, 41 Stat. 1070; renumbered pt. I, Aug. 26, 1935, ch. 687, title II, § 212, 49 Stat. 847.)

TRANSFER OF FUNCTIONS

Federal Power Commission terminated and its functions with regard to licenses and permits for dams, reservoirs, or other works for development and improvement of navigation and for development and utilization of power across, along, from, or in navigable waters under this subchapter transferred to Federal Energy Regulatory Commission by sections 7172(a)(1)(A) and 7293 of Title 42, The Public Health and Welfare.

§ 806. Time limit for construction of project works; extension of time; termination or revocation of licenses for delay

The licensee shall commence the construction of the project works within the time fixed in the license, which shall not be more than two years from the date thereof, shall thereafter in good faith and with due diligence prosecute such construction, and shall within the time fixed in the license complete and put into operation such part of the ultimate development as the commission shall deem necessary to supply

the reasonable needs of the then available market, and shall from time to time thereafter construct such portion of the balance of such development as the commission may direct, so as to supply adequately the reasonable market demands until such development shall have been completed. The periods for the commencement of construction may be extended once but not longer than two additional years and the period for the completion of construction carried on in good faith and with reasonable diligence may be extended by the commission when not incompatible with the public interests. In case the licensee shall not commence actual construction of the project works, or of any specified part thereof, within the time prescribed in the license or as extended by the commission, then, after due notice given, the license shall, as to such project works or part thereof, be terminated upon written order of the commission. In case the construction of the project works, or of any specified part thereof, has been begun but not completed within the time prescribed in the license, or as extended by the commission, then the Attorney General, upon the request of the commission, shall institute proceedings in equity in the district court of the United States for the district in which any part of the project is situated for the revocation of said license, the sale of the works constructed, and such other equitable relief as the case may demand, as provided for in section 820 of this title.

(June 10, 1920, ch. 285, pt. I, § 13, 41 Stat. 1071; renumbered pt. I, Aug. 26, 1935, ch. 687, title II, § 212, 49 Stat. 847.)

REFERENCES IN TEXT

Proceedings in equity, referred to in text, were abolished by the adoption of rule 2 of the Federal Rules of Civil Procedure, set out in the Appendix to Title 28, Judiciary and Judicial Procedure, which provided that "there shall be one form of action to be known as 'civil action' ".

TRANSFER OF FUNCTIONS

Federal Power Commission terminated and its functions with regard to licenses and permits for dams, reservoirs, or other works for development and improvement of navigation and for development and utilization of power across, along, from, or in navigable waters under this subchapter transferred to Federal Energy Regulatory Commission by sections 7172(a)(1)(A) and 7293 of Title 42, The Public Health and Welfare.

§ 807. Right of Government to take over project works

(a) Compensation; condemnation by Federal or State Government

Upon not less than two years' notice in writing from the commission the United States shall have the right upon or after the expiration of any license to take over and thereafter to maintain and operate any project or projects as defined in section 796 of this title, and covered in whole or in part by the license, or the right to take over upon mutual agreement with the licensee all property owned and held by the licensee then valuable and serviceable in the development, transmission, or distribution of power and which is then dependent for its use

fulness upon the continuance of the license, together with any lock or locks or other aids to navigation constructed at the expense of the licensee, upon the condition that before taking possession it shall pay the net investment of the licensee in the project or projects taken, not to exceed the fair value of the property taken, plus such reasonable damages, if any, to property of the licensee valuable, serviceable, and dependent as above set forth but not taken, as may be caused by the severance therefrom of property taken, and shall assume all contracts entered into by the licensee with the approval of the Commission. The net investment of the licensee in the project or projects so taken and the amount of such severance damages, if any, shall be determined by the Commission after notice and opportunity for hearing. Such net investment shall not include or be affected by the value of any lands, rights-of-way, or other property of the United States licensed by the Commission under this chapter, by the license or by good will, going value, or prospective revenues; nor shall the values allowed for water rights, rights-of-way, lands, or interest in lands be in excess of the actual reasonable cost thereof at the time of acquisition by the licensee: Provided, That the right of the United States or any State or municipality to take over, maintain, and operate any project licensed under this chapter at any time by condemnation proceedings upon payment of just compensation is expressly reserved.

(b) Relicensing proceedings; Federal agency recommendations of take over by Government; stay of orders for new licenses; termination of stay; notice to Congress

In any relicensing proceeding before the Commission any Federal department or agency may timely recommend, pursuant to such rules as the Commission shall prescribe, that the United States exercise its right to take over any project or projects. Thereafter, the Commission, if its does not itself recommend such action pursuant to the provisions of section 800(c) of this title, shall upon motion of such department or agency stay the effective date of any order issuing a license, except an order issuing an annual license in accordance with the proviso of section 808(a) of this title, for two years after the date of issuance of such order, after which period the stay shall terminate, unless terminated earlier upon motion of the department or agency requesting the stay or by action of Congress. The Commission shall notify the Congress of any stay granted pursuant to this subsection.

(June 10, 1920, ch. 285, pt. I, § 14, 41 Stat. 1071; renumbered pt. I and amended, Aug. 26, 1935, ch. 687, title II, §§ 207, 212, 49 Stat. 844, 847; Aug. 3, 1968, Pub. L. 90-451, § 2, 82 Stat. 617; Oct. 16, 1986, Pub. L. 99-495, § 4(b)(2), 100 Stat. 1248.)

AMENDMENTS

1986-Subsec. (b). Pub. L. 99-495 struck out first sentence which read as follows: "No earlier than five

'So in original. Probably should be "it".